an element in the wbs was estimated to require 1 month for completion with 1000 hours of labor and a burdened cost of $50k. the task was completed in 1000 hours but a burdened cost of $60k. the most likely reason for the increase would be:

A、higher salaried employees were assigned.

B、overtime was required.

C、the overhead rate increased.

D、employee salaries had increased.

E、any of the above

查看答案 收藏题目 分享题目 举报题目