there are two major types of reserves used on projects. the ( ) is for (usually major) scope changes that were not considered as part of the original plan, whereas the ( ) is to compensate for minor changes in estimating, escalation factors.

A、management reserve, unplanned allowance fund.

B、management reserve, contingency.

C、contingency fund, management reserve.

D、unplanned allowance fund, budgetary reserve.

E、unplanned reserve, planned reserve.