加载中...
单选题 职业资格-PMP

The range of time allowed for an activity to be completed in is the ( ).

A、Planned time (Duration).

B、Float time (LS - ES, or LF - EF).

C、Critical time (when ES = LS, or EF = LF).

D、Scheduled time (LF - ES).

E、Event.