  • 单选题 职业资格-PMP

    management reserve is generally intended to be used to:

    A、implement additional unbudgeted scope

    B、compensate for inaccurate estimates

    C、cover major unforeseen catastrophes

    D、cover unforeseen problems in the project

    E、all of the above.

  • 单选题 职业资格-PMP

    which of the following is most closely associated with pure risk:

    A、profit and loss

    B、personnel turnover

    C、insurance

    D、market fluctuations

    E、a and d only

  • 单选题 职业资格-PMP

    the project manager must receive reports and briefings from engineers, contracting officers, procurement personnel and marketing people. the project manager's communication dilemma is one of:

    A、encoding

    B、decoding

    C、choice of a medium

    D、one-way communication

    E、all of the above.

  • 单选题 职业资格-PMP

    a project element which lies between two events is called:

    A、an activity.

    B、a critical path method.

    C、a slack milestone.

    D、a timing slot.

    E、a calendar completion point.

  • 单选题 职业资格-PMP

    employee unions would most likely satisfy which level in maslow's hierarchy of needs?

    A、belonging

    B、self-actualization

    C、esteem

    D、safety

    E、empowerment

  • 单选题 职业资格-PMP

    management calls a meeting to explain to all employees the new benefits package for the rank and file. this is an example of:

    A、upward communication

    B、downward communication

    C、one-way communication

    D、two-way communication

    E、none of the above.

  • 单选题 职业资格-PMP

    the technique most commonly used to determine the profitability of a project includes ( ) methods.

    A、net present value (npv).

    B、return on investment (roi).

    C、discounted cash flow (dcf)

    D、payout time and risk sensitivity analysis.

    E、all of the above.

  • 单选题 职业资格-PMP

    the basic terminology for networks includes:

    A、activities, events, manpower, skill levels and slack.

    B、activities, documentation, events, manpower and skill levels.

    C、slack, activities, events, and time estimates.

    D、time estimates, slack, sponsorship involvement, and activities.

    E、time estimates, slack time, report writing, life cycle phases, and crashing times.

  • 单选题 职业资格-PMP

    which of the following is closest to juran's definition of quality:

    A、conformance to requirements.

    B、fitness for use.

    C、continuous improvement.

    D、customer focus.

    E、all of the above.

  • 单选题 职业资格-PMP

    which of the following are part of the purchasing cycle:

    A、define need

    B、prepare and issue purchase order

    C、inspect incoming goods

    D、all of the above.

    E、a and b only