job continuity would be an example of ( ) in maslow's hierarchy of needs.
A、self-actualization
B、esteem
C、physiological
D、belonging
E、safety
it is argumentative whether project managers actually control costs. which of the following is the most common element over which the project manager may have some degree of control?
A、direct labor dollars
B、direct labor hours.
C、overhead rates.
D、procurement costs.
E、none of the above.
total project risk can be defined as:
A、the sum of the probabilities of project risks events times the sum of consequences of those risks
B、the sum of the products of each project risk event times its consequences
C、the sum of the consequences of all project risk events
D、the sum of the probabilities of all project risk events
E、1 - the sum of the probabilities of all project risk events.
the major reason why a project manager would use written instead of oral communication is:
A、documentation
B、feedback
C、cost
D、barrier elimination
E、all of the above.
which of the following is equivalent to a lump sum contract:
A、fixed price contract
B、price fixing contract
C、purchase order
D、all of the above.
E、b and c only
back charges refers to:
A、transferring charges from sub-contractors to the owner
B、adjusting payments to reflect late invoices consequence
C、the cost of corrective action taken by the owner and charged to the contractor for non-conformance
D、gaining restitution from the owner for non payment
E、c and d only
the utility of a risk seeker is:
A、negatively exponential
B、positively skewed
C、increasing
D、decreasing
E、symmetrical
communication in both project and non-project-driven organizations should occur in directions.
A、one
B、two
C、three
D、four
E、five
according to herzberg, which of the following is a motivational factor?
A、pay
B、hygiene needs
C、achievement
D、working conditions
E、vacation time
japanese quality control has improved dramatically in the last 30 years for all of the following reasons except:
A、the use of quality circles.
B、small, continuous improvements in quality control.
C、the use of worker suggestion systems.
D、the use of quality control charts.
E、focusing quality control efforts on production outputs.